Toshiba GR200 Series Instruction Manual page 80

Centralized busbar protection ied
Hide thumbs Also See for GR200 Series:
Table of Contents

Advertisement

Target CB tripped by CBF re-trip
(ii)
Figure 2.2-8 shows a CBF re-trip of the target CB. If the OCCBF relay continues to operate a
CBF re-trip command is issued to the target CB if the setting time of [TCBF-RE_CH*] has
elapsed. Unless the CB fails to operate, the OCCBF relay is reset by the CBF re-trip. This may
happen when the CBF function is started by mistake, for example by personnel error during
relay testing, if the bay protection is used to initiate the CBF there is a risk that test personnel
may forget to isolate the start signal to the CBF. If the protection under test trips and there is
sufficient load current flowing through the circuit breaker, there is a risk of a back-trip
command being issued to trip all back-up (adjacent) circuit breakers. This may cause a severe
disturbance. With the re-trip function the consequence of such an error will be limited to the
tripping of only one circuit breaker.
The CBF Zone-trip timer does not time out and the CBF function is reset.
Fault
Fault current
Closed
Adjacent CB
Open
Unsuccessful
Closed
Target CB
Open
GEN.TRIP signal
OCCBF_CH* relay
Re-trip
Zone-trip
TCB: operating time of the target CB
TOC: reset time of the OCCBF element in CH*
Figure 2.2-8 Timing chart (Target CB tripped by CBF re-trip)
Timer set with [TCBF-RE_CH*]
Timer set with [TCBF-ZONE_CH*]
- 66 -
TCB
TOC
'OCCBF relay' resets before TCBF-ZONE timer elapses
Centralized GRB200
(Soft: 030, 031, 032, 033, 034)
6F2S1931 (0.20)