108/128 Decommissioning

Overall machinery/system
Bosch Rexroth AG, CytroBox, RE 51057-B/11.19
11 Decommissioning

11.1 Preparing for decommissioning

Provide collecting containers that are large enough to accommodate the total
hydraulic fluid volume.
The total volume of the hydraulic system comprises the volumes of the oil tank,
the line system, the drives, etc.
Always observe applicable instructions for the overall machinery/system.
Unless these operating instructions provide different information, proceed as
follows:
– Prevent any hazards due to machinery in the vicinity.
– Unauthorized personnel must not be allowed access to the working area.
– Lower and securely support all loads.

11.2 Decommissioning process

Switch off the power supply and secure the system against restarting.
Switch off the hydraulic pressure supply and secure it.
Make sure that all relevant system parts are depressurized and de-energized.
Empty the tank with a filling unit via the filling coupling (connector plug) type
CEJN567-G1/2-020-105676200, see Fig. 8, pos. 15 on page 51.
– In this connection, ensure complete draining of the lines and actuators.
If necessary, carry out bleeding measures.
Decommission the overall machinery/system as described in the overall
machinery/system operating instructions.