7.3 Performing an online configuration for the D4x5-2
6. Click "Create" to start the automatic configuration. As soon as automatic commissioning
has been run through, an upload operation (Load to PG) is performed automatically.
Note
The components' firmware is upgraded or downgraded automatically based on the firmware
version on the CF card and the firmware version on the SINAMICS components
(DRIVE‑CLiQ components, TB30, CBE30-2, Power Modules, etc.).
The update procedure can take several minutes and is indicated in the "Automatic
Configuration" dialog box by the following message:
State of the drive unit: Automatic FW update of DRIVE-CLiQ components
A firmware update on DRIVE‑CLiQ components is indicated by the RDY LED flashing red
and green:
● FW update running: RDY LED flashes slowly (0.5 Hz)
● FW update complete: RDY LED flashes quickly (2 Hz), POWER ON required
These flashing patterns are also displayed by the yellow RDY LED on the SIMOTION D/
CX32‑2 and indicate that a firmware update is being carried out on components connected
to the SIMOTION D/CX32‑2 or that all components have completed the firmware update.
Components requiring POWER ON following a firmware update signal this by means of the
fast flashing RDY LED. Go offline with SCOUT and switch the 24 V supply to the relevant
components off/on (POWER ON) to initialize.
CBE30-2 option board:
During the firmware update, the OPT LED of the SIMOTION D module and the SYNC LED
of the CBE30-2 flash green.
206
Commissioning and Hardware Installation Manual, 03/2018, A5E33441636B
SIMOTION D4x5-2

Hide quick links:

Advertisement

Table of Contents
loading

This manual is also suitable for:

Simotion cx32-2Simotion cbe30-2Simotion tb30

Table of Contents