Figure 4-1 Sticking the positioning label
Step 2 Drill four holes with a diameter of 5.5 mm on the ceiling or wall based on the marks on the
positioning label, as shown in Figure 4-2.
Issue 03 (2013-02-28)
NOTE
If the rear cabling mode is used, drill a hole on the ceiling or wall, as instructed by the red circle in
Figure 4-1. (Later descriptions in this manual assume that the rear cabling mode is used.)
If the side cabling mode is used, route the multi-connector cable out from the side gap at the bottom
of the IPC.