Pipe Installation
● Clean the external water pipes before connecting them to the water inlet and
outlet pipes of the coil pipes of the unit.
● Water pipes need to be prepared onsite. If galvanized steel pipes are used,
stainless steel connectors must be used to ensure sealing.
● Connect the water inlet and outlet pipes of the unit using pipe thread
connectors. When connecting the water pipes, do not exert excessive force to
avoid damage to the coil pipes. (When connecting the pipes, use two pipe
wrenches or chain pliers.)
● After installing water pipes, install supports to secure the pipes.
Figure 5-9 Water refill pipe routing
Figure 5-10 Drainpipe routing (end pipe routing)
(1) Drainage manifold
Issue 03 (2021-04-20)
NO TICE
Copyright © Huawei Digital Power Technologies Co., Ltd.
5 System Installation (FDC Scenario)
(2) Water trap