UPS5000-H-(400 kVA-800 kVA)
User Manual (100 kVA Power Modules)
Knock the expansion bolt into the hole until the expansion sleeve completely fits
into the hole. The expansion sleeve must be completely buried under the ground
to facilitate subsequent installation.
Figure 6-89 Drilling a hole and installing an expansion sleeve
(1) M12 bolt
(4) Expansion sleeve
Step 3 Remove the UPS cabinet side panels.
Step 4 Remove the front panel from the bottom cabling cabinet.
Step 5 Install anchor baffle plates at the rear of the cabinets.
Figure 6-90 Installing anchor baffle plates at the rear of the cabinets
Step 6 Combine the bottom cabling cabinet.