Step 6 Install the removed side panels on both sides of the bottom cabling cabinet.
Step 7 Install top frames.
Figure 6-77 Installing top frames
Step 8 Install mounting plates.
Issue 03 (2021-08-03)
Figure 6-76 Installing signal cables between the UPS and the SmartLi