10.4.3 Function test

10.4.4 Completing work

A6V10421795_en--_k
WARNING
Alarming and ↑ RT transmission are activated during testing.
You must do the following:
Inform fire brigade.
Inform owner of the building.
1. Execute lamp test. See chapter 'Lamp test [➙ 79]'.
2. Test each device (detector, MCP, etc.) individually and check the correctness
of the system behavior (e.g. alarm device activation, RT fire, RT fault, Fire
control, etc.). See chapter 'Detection test [➙ 77]'.
3. Make sure that the panel is in normal operation, the buzzer and all system
parts are enabled.
 The function test is finished.
1. Check date and time on the panel display. If they are not correct, modify them.
See chapter 'Set date & time [➙ 87]'.
2. Secure the housing cover with a screwdriver.
3. Complete the installation label (top right of the housing) with the commissioning
date.
 The system can now be handed over to the customer.
Commissioning
General commissioning steps
10
113 | 151

Advertisement

Table of Contents
loading

This manual is also suitable for:

Fc362 seriesFc361-zzFc361-zaFc362-zzFc362-za

Table of Contents