4.3.5 Installing Water Pipes

The designed height of the water trap must meet the requirements specified in
Figure
Figure 4-10 Designed height of the water trap
Installing Water Pipes
Water pipes need to be prepared onsite. If galvanized steel pipes are used,
stainless steel connectors must be used to ensure sealing.
After water pipes are installed, wrap thermal insulation foam.
Figure 4-11 Drainpipe routing (end pipe routing)
(1) Drainpipe
Issue 02 (2021-04-15)
NO TE
● The air duct must be wrapped with thermal insulation foam, and the thickness of the
thermal insulation foam must be greater than or equal to 3 cm.
● The joint between the air duct and the unit should be sealed to prevent air leakage.
Generally, the sealing cotton is pressed inside the flange of the air duct or sealant is
applied to the flange after installation.
3-11.
NO TE
It is recommended that the height of segment B be a smaller value.
Copyright © Huawei Technologies Co., Ltd.
4 System Installation (FDC Scenario)
(2) Water trap
77

Hide quick links:

Advertisement

Table of Contents
loading

This manual is also suitable for:

Fusioncol8000-e240h4

Table of Contents