FusionCol8000-E240 Modular Indirect Evaporative
Cooling System
User Manual
3.4.4.5 FE Teamwork + FE Monitoring
Step 1 Connect teamwork and monitoring communications cables.
Networking
Protocol
Note
Figure 3-27 Connecting communications cables
----End
3.4.5 Installing Power Cables
Procedure
Step 1 Route power cables through the external cable holes.
Step 2 Open the electric control box outside the unit.
Step 3 Connect one end of the primary and backup power cables to the primary/backup
power supply terminals/PE terminal through the cable holes in the electric control
box of the unit, and connect the other end to the power supply.
Figure 3-28 Connecting power cables
Issue 02 (2021-04-15)
Teamwork
MAC_CAN
One teamwork network
supports a maximum of 16
smart cooling products.
NO TE
Customers can purchase Huawei's switch and NetEco for the monitoring system.
Copyright © Huawei Technologies Co., Ltd.
3 System Installation (Building Scenario)
Monitoring
Modbus-TCP/SNMP
-
56