FusionModule1000A20 Prefabricated All-in-One Data
Center
Installation Guide
Figure 6-23 Wiring diagram
Step 4 Install thermal insulation foam on pipes.
Wrap the electric heating belt before wrapping the thermal insulation foam, and the thermal insulation
foam covers the electric heating belt. Verify that the thermal insulation foam can withstand a temperature
greater than or equal to 200° C.
----End