Commissioning
5.4 Quick commissioning using the BOP-2 operator panel
5.4.2

Start quick commissioning and select the application class

Starting quick commissioning
Requirements
● The power supply is switched on.
● The operator panel displays setpoints and actual values.
Procedure
Proceed as follows to carry out quick commissioning:
Press the ESC key.
Press one of the arrow keys until the BOP-2 displays the "SETUP" menu.
To start quick commissioning, in the "SETUP" menu, press the OK key.
If you wish to restore all of the parameters to the factory setting before the quick commissioning,
proceed as follows:
1. Press the OK key.
2. Switchover the display using an arrow key: nO → YES
3. Press the OK key.
Whether the inverter displays this commissioning step depends on the Power Module being
used:
● PM230 or PM250 Power Modules:
The inverter skips step DRV APPL.
● PM240‑2, PM240P‑2 or PM330 Power Modules:
select the application class:
Select the motor standard:
● KW / 50HZ: IEC
● HP / 60HZ: NEMA
● KW / 60HZ: IEC 60 Hz
Specify the overload capability of the inverter:
● HIGH OVL: Load cycle with "High Overload"
● LOW OVL: Load cycle with "Low Overload"
154
Quick commissioning with application classes (Page 160)
Overload capability of the inverter (Page 438)
Converter with the CU230P-2 Control Units
Operating Instructions, 09/2017, FW V4.7 SP9, A5E34257946B AE