NetCol8000-C190 In-room Chilled Water Smart
Cooling Product
User Manual (2022, Singapore STT)
3.6.3 Installing Power Cables
Procedure
Step 1 Route the power cables through the power cable hole to the electrical box.
Step 2 Connect the L1, L2, L3, N, and PE wires of the active and standby power cables to
the corresponding terminals or screws at QF1 and QF2 of the electrical box.
Figure 3-26 Installing power cables
----End
3.6.4 Installing Signal Cables
Issue 02 (2022-03-30)
Copyright © Huawei Technologies Co., Ltd.
3 Installation
49