Checking the outside of the SICHARGE UC dispenser

Maintenance interval
After commissioning, carry out the tests at the following intervals:
• 6 months after commissioning
• 12 months after commissioning
After the first year, carry out the tests every 12 months.
Run the tests at shorter intervals as required by the ambient conditions of the SICHARGE UC dispenser.
Visual check of the outside
Check the following:
1. Visible damage to the cabinet exterior
2. Correct position of the charging plug
3. Correct position of the charging plug holder
4. Ventilation openings
5. The charging plug for signs of wear, humidity, dust or corrosion
6. The charging cable for damage and wear
7. Check the display for contamination and damage (if available)
8. Function of the display (if available)
9. Function of the LED display (if available)
Noise testing
Check the fan for atypical running noises.