POST INSTALLATION TEST
FCCS Network Connection Test
3.2 ATTCON Connection Test (via FCCS)
Perform the ATTCON connection test, using the following procedure.
3.2.1
ATTCON Call Origination Test
STEP 1: Dial the operator access code (normally "0"), from STN A in Node A.
STEP 2: Confirm that the ATT lamp flashes and ringer sounds at each ATTCON in Node B.
STEP 3: Answer the call by pressing the ATND key.
STEP 4: Confirm the speech condition is sufficient (no noise, not one-party speech, etc.).
STEP 5: Release the call by pressing the CANCEL key.
STEP 6: Replace the handset of STN A in Node A.
3.2.2
ATTCON Call Termination Test
STEP 1: Press a LOOP key on an ATTCON in Node B.
STEP 2: Dial the Telephone Number of STN A.
STEP 3: Confirm the ringer sounds properly at STN A.
STEP 4: Answer the call and confirm the speech condition is sufficient (no noise, not one-way speech, etc.).
STEP 5: The operator at the ATTCON releases the call by pressing the CANCEL key.
STEP 6: Replace the handset of STN A in Node A.
Operator Access
Node A (Self-Node)
Code "0"
STN A
LC
TELN: 410000
STN: 2000
TELN: Telephone Number STN: Physical Station Number
Figure 6-9 ATTCON Connection Test (origination) via FCCS
CHAPTER 6
Page 140
Revision 3.0
FCCS
ND-70185 (E)
Get other manuals https://www.bkmanuals.com
Node B
ATI
Check
Check
ATTCON