Performing Flushing Cycle - Bosch 70 Series Instruction Manual

Axial piston fixed motor
Table of Contents

Advertisement

Procedure
To connect the axial piston unit to the hydraulic system:
1.
Remove the protection plugs and threaded plugs at the ports at which the
connections are to be made according to the hydraulic schematic.
2.
Make sure that the sealing surfaces of the hydraulic ports and functional surfaces
are not damaged.
3.
Use only clean hydraulic lines or flush them before installation. (Observe
Chapter 7.5 "Performing flushing cycle" on page 35 when you flush out the
entire system.)
4.
Connect the lines in accordance with the installation drawing and the machine
or system schematic. Check whether all ports are connected or plugged with
threaded plugs.
5.
Tighten the fittings correctly (note tightening torques). Mark all correctly
tightened fittings, e.g., with a permanent marker.
6.
Check all pipes and hose lines and every combination of connecting pieces,
couplings or connecting points with hoses or pipes to ensure they are in
condition for safe working.
Relationship between direction of rotation and flow direction:
Clockwise rotation:
Counter-clockwise rotation:

7.5 Performing flushing cycle

In order to remove foreign particles from the system, Bosch Rexroth recommends a
flushing cycle for the entire system before the first commissioning. To avoid internal
contamination, the axial piston unit must not be included in the flushing cycle.
The flushing cycle must be performed with an additional flushing unit. Follow the
instructions of the flushing unit's manufacturer for the exact procedure during the
flushing cycle.
A to B
B to A
RE 91071-01-B/03.2015, A2FM/A2FE Series 70, Bosch Rexroth AG
Installation
35/52