Huawei FusionDC1000A Maintenance Manual page 80

Prefabricated all-in-one data center
Hide thumbs Also See for FusionDC1000A:
Table of Contents

Advertisement

FusionDC1000A Prefabricated All-in-One Data
Center
Maintenance Guide (IT Scenario)
4.
Step 13 Pull the smart cooling product.
1.
2.
3.
Issue 01 (2021-04-20)
Figure 4-16 Placing the steel plate and pipes
(1) 0.5 m long steel pipe
Push the smart cooling product until it is separated from the base and placed
onto the two steel pipes.
NO TICE
Adjust the positions of the two steel pipes and the distance in between to
ensure that the smart cooling product is evenly carried on the two steel pipes.
Slide the smart cooling product to the cold aisle.
Place the three 0.5 m long steel pipes evenly in the long aisle near the
entrance of cold aisle B.
Push the smart cooling product completely onto the three 0.5 m long steel
pipes, and move the smart cooling product along the long aisle to the pre-fab.
module side door.
Copyright © Huawei Technologies Co., Ltd.
4 Parts Replacement
(2) 3 mm thick steel plate
72