FusionModule2000 Smart Modular Data Center
Installation Guide
Figure 11-1 Cable trough components
(1) Partition plate
When installing cable troughs, be aware of rPDU cables and industrial connectors:
Figure 11-2 rPDU cable routing on the top of a cabinet
(1) Weak-current cable trough
Issue 02 (2018-03-31)
Cold aisle scenario: Install cable troughs above the front door of a cabinet first. When
installing cable troughs above the rear door, move the cables to the open area of the cable
troughs. After installing cable troughs above the rear door, place the rPDU cables and
industrial connectors inside the cable troughs above the front door. For details, see
Figure
11-2.
Hot aisle scenario: After cable troughs above the front and rear doors are installed, place
the rPDU cables and industrial connectors in the cable trough above the rear door.
After rPDU cables and industrial connectors are placed, bind the cables to the cable
trough using cable ties.
The strong-current cable trough must be close to the aisle containment.
Huawei Proprietary and Confidential
Copyright © Huawei Technologies Co., Ltd.
11 Installing Cable Troughs and Cable Trays
(2) Vertical plate
(2) Strong-current cable trough
(3) Tray