Flange-Mounted Installations - ABB AZ10 Operating Instruction

Combustion gas analysis.
Hide thumbs Also See for AZ10:
Table of Contents

Advertisement

14
A Z 1 0 O X YG E N A N A LY Z E R | C O M B U S T I O N G A S A N A LY S I S | O I/A Z 1 0 - E N R E V. A
...6 Installation

Flange-mounted installations

WARNING
Failure to observe this warning will result in serious injury.
Before fitting the probe, ensure that the boiler is off and the
flue is cool enough to touch.
If hot process gases are flowing through the flue when the
probe intake tube is inserted, it will direct those gases
toward the operator.
Notes
• This procedure is for AZ10 probes mounted to customer-
supplied/installed flanges – see page 11 for threaded
NPT/BSP installations.
• The gasket joints must be gas tight otherwise errors in the
O2 readings will occur.
Referring to Figure 10:
1 Fit a suitable mating flange (customer-supplied)
the flue wall.
2 Secure flange
to the flue-mounted mating flange
B
using suitable fixings
C
3 Locate a gasket
D
over the studs on flanged boss
see Notes, left.
4 Insert the probe intake tube
ensuring that the open side of the intake tube tip faces into
the gas flow – see Figure 7, page 10 and Warning (left).
5 Align the bolt holes
F
in the probe intake tube flange with
the studs on the adaptor ensuring that the open side of the
intake tube tip continues to face into the gas flow.
An arrow
G
is stamped on the tube flange to assist with
orientation.
6 Locate a gasket
H
over the studs on the adaptor –
see Notes, left.
7 Fit the probe body
I
over the studs on the adaptor
ensuring Company name is uppermost.
8 Secure the probe and gasket using six M6 nuts and
washers
.
J
A
(not-supplied).
B
E
through the adaptor,
to
A