Adjustment > Basic Adjustment > Height Adjustment > Height adjustment
Height Adjustment
In the case of jam with this equipment, follow the steps below to execute height adjustment.
■ Checking the height
1) Check height between the finisher and the host machine. Check whether the height
difference between the upper right surface [1] of the finisher and the upper left surface [2]
of the host machine is within +/- 2mm.
5
Adjustment > Basic Adjustment > Height Adjustment > Height adjustment
[1]
[2]
F-5-1
2) If the height difference is +/- 2mm or more, execute height adjustment.
NOTE:
Use 4 casters [1] shown in the figure for height adjustment.
[1]
■ Height adjustment
1) Separate the finisher from the host machine.
2) Remove the spanner [1] from the front cover.
• 1 screw [2]
[1]
[2]
5-3
[1]
F-5-2
F-5-3
5-3