This chapter describes how to unpack and check the delivered equipment to ensure that all the
materials are included and intact.
Context
l After a cabinet or an BBU is unpacked, it must be powered on within 7 days.
l After an RRU is unpacked, it must be powered on within 24 hours.
Procedure
Step 1 Check the total number of articles in each case according to the packing list.
If ...
The total number tallies with the packing
list
The total number does not tally with the
packing list
Step 2 Check the exterior of the packing case.
Issue ()
4
NOTE
When transporting, moving, or installing the equipment, components, or parts, you must:
l
Ensure that they are transported in the delivered packages instead of being unpacked or in non-
standard packages. If boards are used for a trial and then transported to sites, pack the boards again
before transportation.
l
Prevent them from colliding with doors, walls, shelves, or other objects.
l
Wear clean gloves, and avoid touching the equipment, components, or parts with bare hands, sweat-
soaked gloves, or dirty gloves.
CAUTION
Huawei Proprietary and Confidential
Copyright © Huawei Technologies Co., Ltd.

Unpacking the Equipment

Then ...
Go to
Step
Find out the cause and report any missing
articles to the local Huawei office.
4 Unpacking the Equipment
2.
31