Guidelines For Cable Connections; Figure 29. Cable Connection Procedure - Samsung 310 5G CPE Installation Manual

Outdoor unit
Hide thumbs Also See for 310 5G CPE:
Table of Contents

Advertisement

Guidelines for Cable Connections

The figure below depicts the sequence of operations for connecting cables to the
system.

Figure 29. Cable Connection Procedure

Cable Path Inspection
Cable Cutting
Cable Installation
Connector Attachment
Cable Binding
Identification Tag Attachment
When cutting the cable after installation, ensure that the connector is disconnected.
The cable installation while the connector is connected to the system may cause
contact failure, or damage to the assembled connector and the cable, due to cable
tension or operator mistakes.
The sequence of cable cutting and installation of the cable workflow can be
changed depending on the field situation such as "cutting after installing" or
"installing after cutting".
5G CPE Outdoor Installation Manual v1.0
Copyright © 2018, All Rights Reserved.
When assembling the
connector at the site
Confidential
Chapter 3 Connecting Cables
Connector Assembly
31

Hide quick links:

Advertisement

Table of Contents
loading

Table of Contents