Guidelines for Cable Connections
The figure below depicts the sequence of operations for connecting cables to the
system.
Figure 29. Cable Connection Procedure
Cable Path Inspection
Cable Cutting
Cable Installation
Connector Attachment
Cable Binding
Identification Tag Attachment
When cutting the cable after installation, ensure that the connector is disconnected.
The cable installation while the connector is connected to the system may cause
contact failure, or damage to the assembled connector and the cable, due to cable
tension or operator mistakes.
The sequence of cable cutting and installation of the cable workflow can be
changed depending on the field situation such as "cutting after installing" or
"installing after cutting".