Step 7: Downloading Configuration File
By default, the ProtoNode is setup with G9000 UPS Modbus configuration file. If using a different UPS
model, please go to
http://www.toshiba.com/ind/product_display.jsp?id1=14&id2=30&id3=581
download the correct UPS protocol configuration file.
1. Before attempting to download the protocol configuration file onto the ProtoNode, put the
protocol configuration file (e.g. config-mod.csv) in "Configuration File Folder", by going to
Start|Programs|FieldServerUtilities|Configuration File Folder.
2. From the main menu on RUI, type "d", for the download configuration option.
3. Type "L" to specify the name and extension of the file to be sent to the ProtoNode (e.g.
config-mod.csv). Hit <Enter> when done.
4. The utility will search for the configuration file specified on step 3 (e.g. config-mod.csv) to
download the CSV file onto ProtoNode. On rare occasions where other files need to be
downloaded to the ProtoNode, type 'o' for other files, then type "r" to specify the remote
filename needed on the ProtoNode.
5. When satisfied that the correct file names are specified, type "d" to send the file to the
ProtoNode. The utility will display progress until it is complete.
6. Note: Wait until the utility indicates that the download is complete before resetting the
ProtoNode or you could corrupt the ProtoNode.
7. Once download is complete hit <esc> key to go to the main menu. Type "!" or cycle power
to ProtoNode to put the new firmware into operation.
8. To verify that the protocol configuration file was downloaded successfully, go to the main
menu and look on the top on the main menu to see the UPS model and the protocol (see
figure 4).
Note: If configuring multiple ProtoNode modules, see reference manual.
Note: Make sure that you have the latest display, control board, and ProtoNode firmware
versions installed. Failure to do so can cause communications problems between the
ProtoNode and UPS.
Step 8: Testing and Commissioning of the ProtoNode
1. From the main menu of Remote User Interface, type "o", for Connection Overview, to see
the data traffic flow for each protocol.
ProtoNode Quick Install Guide – 66939-000